The lab manual is attached . The following is the data for setting and consistency of cement, Lab No-2.
Time at the start of mixing, cement with water- 2:20 PM
Initial Setting time achieved (i.e depth of penetration = 25 mm)- 3:05 PM
Final Setting time achieved (i.e the needle no longer penetrates the cement mix and leaves a dent on the surface)- 8:20 PM
Calculate your initial and final setting time using this data. Let me know if you have any questions.

 