Question 1 of 20 5.0 Points Which of the following is NOT an objective mentioned in the text for data gathered from monitoring?

Question 1 of 20 5.0 Points
Which of the following is NOT an objective mentioned in the text for data gathered from monitoring?

A. Promoting team members

Save your time - order a paper!

Get your paper written from scratch within the tight deadline. Our service is a reliable solution to all your troubles. Place an order on any task and we will take care of it. You won’t have to worry about the quality and deadlines

Order Paper Now

B. Keeping management informed

C. Auditing

D. Learning from mistakes
Reset Selection

Mark for Review What’s This?

Question 2 of 20 5.0 Points
The plan-monitor-control cycle is best described as:

A. an open loop process.

B. a closed-loop process.

C. an ad-hoc process.

D. an informal process.
Reset Selection

Mark for Review What’s This?

Question 3 of 20 5.0 Points
Which of the following is used when it is especially difficult to find a direct measure of a variable?

A. Frequency count

B. Raw numbers

C. Surrogates

D. Subjective numeric ratings
Reset Selection

Mark for Review What’s This?

Question 4 of 20 5.0 Points
Which of the following is most closely associated with ordinal rankings?

A. Frequency counts

B. Raw numbers

C. Indicators

D. Subjective numeric rankings
Reset Selection

Mark for Review What’s This?

Question 5 of 20 5.0 Points
Which of the following is NOT a distinct type of report?

A. Exception

B. Special analysis

C. Critical incident

D. Routine
Reset Selection

Mark for Review What’s This?

Question 6 of 20 5.0 Points
Which of the following was NOT listed in the text as a convention for estimating task progress?

A. 50% when task is started and another 50% when it is completed

B. 100% when task is completed and 50% before that

C. Using the ratio of cost expended to total cost budgeted

D. Using the ratio of time expended to the total time scheduled
Reset Selection

Mark for Review What’s This?

Question 7 of 20 5.0 Points
The cost/spending variance is calculated as:

A. AC – EV.

B. EV – PV.

C. PV – EV.

D. EV – AC.
Reset Selection

Mark for Review What’s This?

Question 8 of 20 5.0 Points
Estimated (remaining cost) to completion (ETC) is calculated as:

A. (BAC – EV)/CPI.

B. (BAC – EV)/SPI.

C. (BAC + EV)/CPI.

D. (BAC + EV)/SPI.
Reset Selection

Mark for Review What’s This?

Question 9 of 20 5.0 Points
In earned value analysis:

A. it is desirable to have negative variances for both schedule and spending.

B. it is desirable to have positive variances for both schedule and spending.

C. the schedule variance should be positive and the spending variance negative.

D. the schedule variance should be negative and the spending variance positive.
Reset Selection

Mark for Review What’s This?

Question 10 of 20 5.0 Points
Which of the following is NOT a primary mechanism by which the project manager exerts control?

A. Reviews

B. Personnel assignments

C. Audit reports

D. Resource allocation
Reset Selection

Mark for Review What’s This?

Question 11 of 20 5.0 Points
Which of the following is NOT a component of a control system?

A. Effector

B. Sensor

C. Decision maker

D. Leveler
Reset Selection

Mark for Review What’s This?

Question 12 of 20 5.0 Points
Which of the following is NOT a tool used to aid the project manager in project control?

The post Question 1 of 20 5.0 Points Which of the following is NOT an objective mentioned in the text for data gathered from monitoring? appeared first on Infinitessays.org.