Week 2 WBS Wedding Assignment using MS Project

 

Now is the time to install MS Project. Do that first, then complete the following MS Project homework exercise.

 

The following are MAJOR tasks for a wedding. Use TWO of the tasks to build a Work Breakdown Structure in Microsoft Project.

 

Each major task should have 2 sub-tasks. Each sub-task should have 2 sub-sub tasks. You may add more if you wish or have a need to add more to be sure the major task is complete.

 

The scenarios are these: You have been asked to help your best friend plan a wedding or a family reunion in another city. You have no concern for schedule or budget at the moment, only defining the work that needs to be done for the wedding or reunion to start on time and to be successful. There will be about 100 guests.

 

The major tasks are these (in no particular order… you may order them in a way that is logical to you… AND you may ADD major tasks as you see the need).:

 

Sign a contract for a church and/or reception facility

Invite guests

Provide décor/decorations (this includes flowers)

Provide food and beverages

Provide lodging and transportation for guests

 

 

Now is the time to install MS Project. Do that first, then complete the following MS Project homework exercise.

 

The following are MAJOR tasks for a wedding. Use TWO of the tasks to build a Work Breakdown Structure in Microsoft Project.

 

Each major task should have 2 sub-tasks. Each sub-task should have 2 sub-sub tasks. You may add more if you wish or have a need to add more to be sure the major task is complete.

 

The scenarios are these: You have been asked to help your best friend plan a wedding or a family reunion in another city. You have no concern for schedule or budget at the moment, only defining the work that needs to be done for the wedding or reunion to start on time and to be successful. There will be about 100 guests.

 

The major tasks are these (in no particular order… you may order them in a way that is logical to you… AND you may ADD major tasks as you see the need).:

 

Sign a contract for a church and/or reception facility

Invite guests

Provide décor/decorations (this includes flowers)

Provide food and beverages

Provide lodging and transportation for guests

Your assignment must be completed in Microsoft Project

  • Team 3, “Enterprise Collaboration”

    Marley Dental Clinic Project Charter

    IFSM 438: Project Management

    ITP-1 Project Deliverable – Project Charter

    Gregory Moore Project Manager

    Tiara Locke Deputy Project Manager

    Charles To Documentation Manager

    Samrawit Bayu Financial Manager

    Hossain Ehsan Editor

    Angel Aguilar Research Manager

    Aiesata Gadson Technical Manager

    A. General Information

    Project Title: Marley Dental Clinic Virtualization
    Brief Project Description:  
    Prepared By: Enterprise Collaboration
    Date: 24 January 2016 Version: 2.0

    Customer and Stakeholders:

    Doctor Bob Marley (Donna McKalip, PhD.)

    B. Project Objective:

    Explain the specific objectives of the project. For example: What value does this project add to the organization? How does this project align with the strategic priorities of the organization? What problem will this project solve? What results are expected? What are the deliverables? What benefits will be realized? What problems will be resolved?

     

    C. Assumptions

    List and describe the assumptions made in the decision to charter this project. Please note that all assumptions must be validated to ensure that the project stays on schedule and on budget.

    HIPAA Privacy and Security policies are required for storing and maintaining patient data, along with additional confidentiality and access requirements. The HIPAA Security Rule requires a dental practice to conduct a written risk assessment and develop safeguards to protect electronic patient information. Customer will need to seek expertise to implement HIPAA compliant security measures. (American Dental Association, 2016)

    D. Project Scope

    Describe the scope of the project. The project scope establishes the boundaries of the project. It identifies the limits of the project and defines the deliverables.

    · The requirements for the Integrated Team Project-1 involve implementing an Information Technology network (LAN) for a small dental clinic that will house 13 workers (4 Dentist, 3 Hygienist, 4 Assistants, 1 Bookkeeper and 1 Receptionist). The customer has established a flexible budget of $150,000 with latitude of increase with proper justification. The estimated project completion will be approximately six months, barring design changes, natural disasters and extension beyond the IT project’s control.

    · Patient records will be converted from hard copy files to an on-sight electronic storage database. Such documentation will include billing and insurance claims.

    · Setup online-banking for payments (patient and practice suppliers) and on-line appointment system for patients.

    · Implementation of an IT system to process insurance billing and claims.

    · Only the Dentists will be equipped with his/her own workstation to access necessary records for each patient. Two additional workstations will be in installed, one for the Bookkeeper and Receptionist to share a workstation to process payments and insurance claims and another for the assistants to access patient dental records.

    · Dental office operations will be temporarily (7 days/one week) interrupted while proper wiring and vetting is conducted to commence installation of requisite IT systems.

    List any requirements that are specifically excluded from the scope.

    · Furnishings for the new space to house the team of dentists, hygienists, assistants, bookkeeper and receptionist.

    · (*) The customer should seek expertise in implementing security features to fully comply with such standards, as the scope of the ITP-1 will not involve implementing HIPAA compatible security features.

    · Administration of applications that will be used to maintain patient records, billing information and HIPAA requirements.

    · Concluding the six-month IT project, the contractual duties will be fulfilled. Any following support will require additional agreements/contracts.

     

    E. Project Milestones

    What is the estimated schedule for the project (start to finish?)

    List the major milestones and deliverables of the project.

    .

    Milestones Deliverables Date
    Signed Project Charter Approved Scope & Objectives 26Jan
    ISP Research/Agreement Present all ISP options to Client 1-28 Feb
    Enterprise Resource Planning Research Present all ERP options to Client 1Mar – 30 May
    Final Client Requirements Refine client requirements 30 May
    ISP Installation Internet connectivity 19 Jun
    Office Local Area Network Installation Install all office computers/network 19-21 Jun
    Initial Operation Capability Initial system capability/testing 22 Jun
    Employee Training Train all clinic employee on new system 22-23 Jun
    Full Operational Capability System fully operational 24 Jun
    Convert Old Records Digitize old dental records 26 Jun

    F. Impact Statement

    List the impact this project may have on existing systems or units.

    .

    Potential Impact Systems / Units Impacted
       
       
       
       
       
       
       

    G. Roles and Responsibilities

    Describe the roles and responsibilities of project team members followed by the names and contact information for those filling the roles. The table below gives some generic descriptions. Modify, overwrite, and add to these examples to accurately describe the roles and responsibilities for this project.

    Sponsor: Provides overall direction on the project. Responsibilities include: approve the project charter and plan; secure resources for the project; confirm the project’s goals and objectives; keep abreast of major project activities; make decisions on escalated issues; and assist in the resolution of roadblocks.
    Name Email / Phone
    Doctor Bob Marley(Donna McKalip, PhD) Donna.McKalip@faculty.umuc.edu
    Project Manager: Leads in the planning and development of the project; manages the project to scope. Responsibilities include: develop the project plan; identify project deliverables; identify risks and develop risk management plan; direct the project resources (team members); scope control and change management; oversee quality assurance of the project management process; maintain all documentation including the project plan; report and forecast project status; resolve conflicts within the project or between cross-functional teams; ensure that the project’s product meets the business objectives; and communicate project status to stakeholders.
    Name Email / Phone
    Gregory Moore Gmoore31@student.umuc.edu
    Tiara Locke (Deputy PM) Tielo502@live.com
    Team Member: Works toward the deliverables of the project. Responsibilities include: understand the work to be completed; complete research, data gathering, analysis, and documentation as outlined in the project plan; inform the project manager of issues, scope changes, and risk and quality concerns; proactively communicate status; and manage expectations.
    Name Email / Phone
    Charles To (Documentation Manager) Chuckto74@yahoo.com
    Hossain Ehsan (Editor) Hehsan023@gmail.com
    Angel Aguilar (Research Manager) Necta79@msn.com
    Samrawit Bayu (Financial Manager) samrijolie@hotmail.com
    Aiesata Gadson (Technical Manager) Aiesata03@gmail.com
    Customer: The person or department requesting the deliverable. Responsibilities include: partner with the sponsor or project manager to create the Project Charter; partner with the project manager to manage the project including the timeline, work plan, testing, resources, training, and documentation of procedures; work with the project team to identify the technical approach to be used and the deliverables to be furnished at the completion of the project; provide a clear definition of the business objective; sign-off on project deliverables; take ownership of the developed process and software.
    Name Email / Phone
    Donna McKalip, PhD Donna.McKalip@faculty.umuc.edu
    Subject Matter Expert: Provides expertise on a specific subject. Responsibilities include: maintain up-to-date experience and knowledge on the subject matter; and provide advice on what is critical to the performance of a project task and what is nice-to-know.
    Name Email / Phone
       
       

    H. Resources

    Identify the initial funding, personnel, and other resources committed to this project by the project sponsor.

    Resource Constraints
    Project Budget $150,000 est.
    Staff Development $45,000
    Customer Support $25,000
    Facilities $55,000
    Equipment $25,000

    I. Project Risks

    Identify the high-level project risks and the strategies to mitigate or avoid them.

    Risk Mitigation Strategy
    Technical  
    Cost Avoid overspending. Record project spending and strict budget constraints
    Client New advertisements, offer new strategies and deals in order to retain customers. Study competitors and offer competitive pricing.
    Environmental Leave room in case of natural disasters occur. Insure all property and equipment
    Schedule Stay within project deadlines and avoid extensions and delays.

    J. Success Measurements

    What are the high level benefits of this project?

    Identify metric and target you are trying to achieve as a result of this project. For example, overall cost savings of $50K or reduce processing time by 25 percent.

     

    K. Signatures

    The signatures of the people below document agreement and approval of the formal Project Charter. The project manager is empowered by this charter to proceed with the project as outlined in the charter. This charter will be

    Customer:    
    Name Signature Date

    Doctor Bob Marley    
     

       
    Project Sponsors:    
    Name Signature Date

         
         
    Project Manager:    
    Name Signature Date

    Gregory Moore