Construction Planning w/microsoft project software
See the link below for the microsoft project file to review the critical path schedule for the construction of a steel building.
You observe that the earthwork activity has been delayed four days. Discuss the advantages and disadvantages for the owner of allowing the contractor to make use of the free float in the activity.
Use of the free float accounts only for three of the lost days. Discuss the possibility of use of one day of the total float.
Are there sufficient benefits to justify modifying the remaining schedule? Explain your answer from the owner’s point of view. Demonstrate your points by modifying the schedule and producing reports in Microsoft Project.
Write your answers in a 2- to 3-page Microsoft Word document.
Cite any sources using APA format on a separate page
Do you need a similar assignment done for you from scratch? We have qualified writers to help you. We assure you an A+ quality paper that is free from plagiarism. Order now for an Amazing Discount!
Use Discount Code “Newclient” for a 15% Discount!
NB: We do not resell papers. Upon ordering, we do an original paper exclusively for you.